CINCINNATI
STREAM RESTORATION
INDIAN CREEK – ODOT
We reconstructed .5 miles of Indian Creek that had been highly eroded with storm damage and was threatening the stability of US RT 27.
Details
ODOT – District 8
Project 140435
Categories
Cincinnati
River Restoration
With permitting getting held up and a tight deadline for ODOT to meet EPA requirements, the 4 month expected duration was squeezed down to 6 weeks. We were able to complete the project within 6 weeks and finished under budget.
District 8 and Mark Haynes Construction, Inc. worked extremely well together to make the project a success.