MADISON
EROSION CONTROL

ARMOR STONE REVETMENT AT TOWNLINE PARK

Our team used 16,000 tons of 3-5 ton Armor stone to construct an Armor stone revetment. 

Details

Madison Townline Park
2017

Categories

Revetment
Lake Erie Erosion

 

For this revetment project, we cleared the bluff and excavated for rock toe, concrete rubble core, and geotextile separation fabric.

The project also included precast concrete steps nestled into the revetment and Army Corp required sand prefill back into the lake.

The project took approximately 3 months.