ARMOR STONE REVETMENT AT TOWNLINE PARK
Our team used 16,000 tons of 3-5 ton Armor stone to construct an Armor stone revetment.
Details
Madison Townline Park
2017
Categories
Revetment
Lake Erie Erosion
For this revetment project, we cleared the bluff and excavated for rock toe, concrete rubble core, and geotextile separation fabric.
The project also included precast concrete steps nestled into the revetment and Army Corp required sand prefill back into the lake.
The project took approximately 3 months.